Guide

From transformer nameplate to available fault current

When the utility letter is incomplete, start from kVA, volts, and percent impedance on the nameplate.

Fault Current & SCCR Label
  1. Read the nameplate: kVA, secondary voltage, %Z.
  2. Choose source modeling: infinite bus, or primary/secondary utility current from a letter when you have it.
  3. Optional tolerance: −10% Z (zTol 0.9) raises available current for a worse-case look.
  4. First feeder: length, conductors, raceway, parallels reduce current at the next point.

Example shape from product vectors (not a substitute for your inputs): 1500 kVA, 480 V, 3.5%Z without tolerance is on the order of 51.5 kA at the terminals before feeder reduction.